Dear Premier Berejiklian and Minister Pavey,
Communities in the Clarence River estuary are concerned about an aspect of the NSW Government's current Pacific Highway construction planning.
The build is
scheduled to start this month and the plant will operate for the next two and a
half years.
Please note
the attitude – local residents are not amused at the high-handed way in which
the NSW Government and RMS went about a cursory declaration of intent.
“What they’re not happy
about is an asphalt batching plant being built right near their houses, using
their only connecting road to the villages”
“We want the highway,
and we want the asphalt plant to be somewhere, but we want it to be away from
our communities where it won’t impact on our health and safety”
“The plant will add a
reported 500 truck moments and 100 car movements per day at peak, or one every
minute, and residents are concerned the additional traffic will create safety
problems, and a bottleneck at their intersection, which they already describe
as “tight” after it was temporarily re-routed. They also cite concerns over
possible health affects the dust may cause for nearby residents.”
We have a resident as
close as 450 metres from the plant who is suffering from lung cancer….Although
Pacific Complete have been made aware of this, since they were first told they
have failed to take action to acknowledge her.”
“We live within one
kilometre of the plant and we found out two weeks ago by letterbox drop”
“We found out last Wednesday
they didn’t tell anyone else. We’ve been around to other residents who are just
outside the area and they had no idea the plant was coming at all.”
I also draw your attention to the content of emails coming out of Iluka:
“Woombah
is surrounded by World Heritage National Park. Within the waterways affected by
run off from the proposed asphalt plant is the organic Solum Farm. Woombah
Coffee will also be affected. Not to mention the multiple organic gardners who sell
at the Yamba Markets and those who grow their own food.
The small community of
Woombah and its neighbour Iluka are places that welcome tourists for the
natural and clean beauty of the environment. An asphalt plant WILL threaten
that.
In addition, the Esk
River at Woombah is fed by many of the creeks and waterways in the bushland
where the asphalt plant is proposed. They will be adversely affected, which
will flow into the Esk which will flow into the Clarence which will affect the
fishing, oyster and prawn industries, on which many make their living. Not to
mention the tourist industry that survives because our area offers a clean
environment with unpolluted air and water.
This proposal is an
outrage. Teven said NO. Woombah says NO as well.”
“What about our kids on
school buses with no seatbelts and the increase in traffic particularly trucks”
“Iluka Naturally, turn
off at the asphalt plant, how ironic.”
For my own part I would add to these expressions of concern the fact that the 80ha, NPWS-managed Mororo Creek Nature Reserve is only est. 98 metres from the western end of the southern boundary of the proposed asphalt batching site.
This protected land parcel is one of the reserves which form part of a
forested corridor linking Bundjalung National Park to the east and the
protected areas of the Richmond Range to the west. It lies within
the boundaries of the Yaegl Local Aboriginal Land Council area, the Clarence
Valley Local Government Area and the Northern Rivers Catchment Management
Authority.
The Mororo Creek Reserve conserves areas of endangered swamp sclerophyll forest, coastal saltmarsh, subtropical coastal floodplain forest and swamp oak floodplain forest.
Most importantly, Mororo Creek and several of its tributaries which run through this reserve empty into the Clarence River Estuary less than est. 2km from the proposed asphalt batching site.
I don’t
pretend to understand why the information sheet contained just one small image
of a section of a Pillar Valley temporary asphalt batching plant with no description
of typical batching plant infrastructure and no Woombah site layout plan at
all, much less one to scale.
There was not
a hint in the information sheet of the range of known issues which can arise during site
construction, plant operation and site rehabilitation.
Those
residents who were originally invited to comment were supplied with less than
rudimentary information on which to assess the desirability of a batching plant
on the designated site.
Given that
the proposed Woombah asphalt batching plant site is est. 2 to 2.5kms as the crow
flies from Clarence River estuary waters
which:
(1) are
covered by Yaegl Native Title;
(2) at certain points are covered by international treaties, including JAMBA, CAMBA,
ROKAMBA;
(3) contain
the second largest area of seagrass (83 ha), the largest area of mangroves (765
ha) and the third largest area of saltmarsh (290ha) in the northern rivers
region [Williams et al 2006 in Northern Rivers
Regional Biodiversity Management Plan 2010];
(4) are part
of the largest combined river-ocean fishery in NSW containing high fisheries value
marine species; and
(5) are a
vital component of regional tourism,
perhaps Premier
Berejiklian and Minister Pavey can answer two vital questions.
1. Is the Woombah asphalt batching plant
site above the 100 year flood level for the lower Clarence Valley flood plain?
Because if it
is not, then the NSW Government’s cavalier attitude to flood risk management
would potentially see toxic waste from asphalt batching flow into the Clarence
River estuary during a flood event – including solid waste and any organic
solvents/hydrocarbons captured in holding ponds for the life of the plant –
along with any nearby excavated plant/road construction materials. After all, extreme flood event
height predictions for that general area are 3.5 to 4.5 mAHD.
2. Why on earth was a decision made to
site the asphalt batching plant and access road at a point along the Pacific
Highway where it would cause the maximum damage to Iluka’s clean, green destination
image and vital tourism trade?
When the NSW Government
first mooted the Pacific Highway upgrade on the North Coast one of the
advantages it canvassed was an increase in tourism numbers due to better road
conditions.
Most of these
visitors holidayed along the Clarence Coast and Iluka is a strong component of that
coastal tourism.
If the NSW Government seriously believes that leaving Woombah-Iluka with only one safe, unimpeded access point
for day, weekend and long-stay visitors, the Yamba to Iluka foot passenger
only ferry, will
not significantly affect tourism numbers over the course of two and a half
years, one has to wonder if it bothered to investigate the issue at all before signing off on the proposed plant site.
The effect of
siting the asphalt batching plant and access road on the designated site will
in all likelihood have the effect of diminishing not growing tourism traffic to
Iluka for a period beyond the years it actually takes to complete the Maclean
to Devil’s Pulpit section of the highway upgrade, as visitor perception of a holiday area can change when industrial level activity becomes visually prominent.
In fact,
looking at satellite images of the site one cannot escape the suspicion that pre-construction
ground preparation had already commenced before any information was sent out to
selected Woombah residents.
Since news of the asphalt batching plan site reached the Lower Clarence and residents began to approach their local state member, there appears to have been a promise made to hold a "drop-in information session" at an unspecified date.
Having experienced NSW departmental drop-in information sessions, I am well aware that they are of limited value as purveyors of anything other that the meagre degree of information found in the aforementioned three page RMS document and, ineffectual as vehicles for genuine community consultation.
The people of Woombah and Iluka deserve better. They deserve a formal information night which canvasses all the issues, with representatives from RMS and the Pacific Highway project team prepared to address concerns and answer questions, as well as representatives of both the Premier and Minister for Roads, Maritime and Freight in attendance as observers.
I’m sure that
all residents and business owners in both Woombah and Iluka would appreciate
both Premier and Minster taking the time to consider these questions and ensure government genuinely consults with both village communities before considering proceeding with any Roads and Maritime Servces site proposal.
Sincerely,