Monday, 3 June 2019

Even when trying to do the right thing are Morrison Government MPs hampered by the penny-pinching ways of their leader


Lismore City Council, 9 April 2019:

As a result of the significant flood event of April 2017 that impacted Lismore in the wake of ex-tropical Cyclone Debbie, Lismore City Council was successful in securing funding for the repair and remediation of a major landslip located at Beardow Street, Lismore Heights.

The initial works at an estimated and approved cost of $1.12 million were funded by the Natural Disaster Relief and Recovery Arrangements (NDRRA).

Contaminated soil was discovered during the restoration process and the cost of remediation is significantly greater than the currently available funding.

When contamination was discovered, eligibility for compensation through the NDRRA changed outside of Council’s control. Council was initially advised that the remediation was eligible for NDRRA funding. This advice was rescinded in late 2018. Negotiations with State agencies continue on this matter and work has stopped while funding issues are resolved.

The area is still contaminated and material needs to be removed. A schedule of works has been developed for full remediation of the site.

The residents in the vicinity of the landslip rightly seek a resolution to the issues associated with access to property, remediation, repairs to the landslip and the lack of clarity around timeframe for completion.

Residents have worked with Council to manage the issues and need closure. They are acutely aware of the process Council needs to follow and have justifiably reached a point where a solution is both required and demanded.

Council’s estimated cost to complete the remediation works is an additional $2.4 million. Council’s December 2018 quarterly budget review provides $700,000 to address the remediation at Beardow Street. Council has been advised of an alternate estimate to complete the works in the order of $5.7 million undertaken by an affected landowner. To date Council has been unable to source the estimated funding shortfall of $1.7 million from Government.

Council is continuing to negotiate a funding outcome. Council held an emergency meeting with Roads and Maritime Services (RMS) on Thursday, 14 March 2019 to find a solution. RMS management attended the site on Tuesday, 19 March 2019 to discuss options. A steering committee has been formed with Council and RMS staff. RMS has made available their geotechnical and environmental specialists, however no alternate solution has been recommended. RMS has made application to the Office of Emergency Management (OEM) for a review of NDRRA eligibility. OEM have escalated the matter to the Federal Government for review of eligibility, however there is no guarantee of success and no time frame for a response. On 29 March 2019 RMS requested Council make application for a Specific Purpose Grant. The outcome of this application is unknown.

The nearest licenced disposal site for the asbestos contamination is in Queensland. The Queensland waste levy comes into effect on 1 July 2019. The levy will add $2 million to the cost of the project in contaminated soil disposal costs.

Council has engaged litigation specialists to provide advice on NDRRA eligibility and options to secure funding. The current advice is to commence with formal correspondence to RMS and/or OEM. This action is underway.

The solution proposed is for Council to obtain the required $1.7 million shortfall from government. We require support from Council for the actions taken to date as well as support for any legal proceedings instigated to recover the restoration costs associated with this natural disaster event. 

On 26 April 2019 during the recent federal election campaign The Northern Star reported that all the candidates, including sitting Nats MP Kevin Hogan, had been asked to commit $10 million to fully remediate this site.

On 27 May 2019 a Lismore journalist stated that Hogan has committed $2.4 million to remediate the asbestos and chemical contaminated landslip. Although it was not explained how he could do this when the new Lib-Nats Coalition Government is weeks away from being sworn in by the Governor-General or why he was committing to less than a quarter of the money requested.

Council is still considering instigating legal proceedings to progress the eligibility of its initial claim for state funding.

No comments: